PT. Adi Putro Wirasejati
Automobile assembler
Masang, Indonesia
"During the project, the following results were achieved …
Annualized saving representing 260% return on our investment
Improvement of meeting effectiveness with clear action plans which has led to precise execution that need to be taken.
Reducing welding machine breakdown by 55%
Reducing lead time in bus (manufacturing) from 62 days/unit to 39.5 days/ unit.
Increase productivity … from 12 [man]-hours/day producing 1.5 unit/day, into 10 hours/day producing 2 units.
I would recommend [this] program to any company looking for improvement and higher profits."
Simon Jethrokusumo
President/Director
"Annualized saving … 260% ROI."
“Reducing lead time in bus (manufacturing) from 62 days/unit to 39.5 days/unit”
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Delta Sport
Sport & fashion wholesaler/retailer
Novi Beograd, Serbia
"… I’m amazed … that we received so much more than you promised to us.
Promised return on investment 1 year after project completion: 171%
Actual return on investment 1 year after project completion: 450% !!!
Cumulative profit improvement is 170% of the plan!!!
[Your] team changed our perception. We are No. 1 in our market, so we thought there was a little to improve over here. [Your] team showed all of us that even if you are the best, there is always a lot to improve."
Goran S. Karić
CEO
… you promised 171% ROI … you delivered 450%!!"
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Dätwyler Cables
Engineering & electronic component distributor
Altdorf, Switzerland
"… We have, together with [your] team, managed to get up productivity of our machines by roughly 15% and the productivity of our employees up by 50% in some cases."
Johannes Müller
Executive Vice President
"… Productivity of our employees up by 50% …"
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Ta Yang Group
Input device manufacturers
Hong Kong
"Project Cum[ulative] Saving till now already exceeds the total cost of the project. Cum[ulative] Annualized Saving ROI is 450%."
Project Cum Savings till now exceeds the total cost of the project. Cum Annualized Saving ROI is 450%.
In Factory II we were able to achieve an increase of material ratio from 62% to 77%.
Labour utilization, in factory 2 was increased from 0.136 to 0.161 KG/HR.
In Factory 1, comparing to our company standards, we improved the overall labour productivity from 74% in July to 90% in October.
David Huang
Executive Director
"… ROI is 450% …"
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Cautre Export
Food processors and distributors
Ho Chi Minh City, Vietnam
"… CAUTRE has made significant achievements as follows:
Company’s output increased by 15%
Recovery of investment during 30 weeks of project [is] calculated at 77%.
Cumulative savings, Annualized return on investment (ROI) is 285%.
Overall, potential of CAUTRE has been realized in 2008 …
Turnover is increased by 40%
Profit is increased 440% "
Ms. Tran Thi Hoa Binh
General Director
"Profit increased 440%"
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
IG Watteeuw
Locomotive transmission manufacturers
Brno, Czech Republic
"Cumulative savings achieved at the end of the project are over €4,000,000 (US $5,294,500), and actual ROI was above 400%."
The number of gear boxes assembled weekly increased from 54 (average of 2008 before the project) to 82 (average of 2009 – which is 52%.
Thanks to the savings achieved our Out-Of-Pocket became positive as of week 8.
The results are also reflected in improvement of EBITDA which increased by 12% points comparing to the beginning of the project and contributed to the plant’s profitability.
Eric Neyrinck
CEO
" … Actual ROI was above 400%…"
“…results are also reflected in improvement of EBITDA which increased by 12% points…”
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Cong Ty Phan Bao Bi Nhua Tan Tien
Flexible Packaging
Ho Chi Minh City, Vietnam
After 38 weeks of the TAN TIEN – IMPAC Project, we together have achieved:
Machine productivity of Printing and Lamination areas of Factory 1 and 2 increased 35%, 34%, 52%, and 12% respectively, the highest in history.
Successful implementation of SMED program to reduce more than 50% of printing machine changeover time from 90-120 minutes to 45 minutes and 30% of Lamination machine changeover time.
The labor productivity of Cylinder factory has increased 42% from 2360cm2/manday to 3341cm2/manday.
The productivity of Proofing section-Cylinder factory has increased 300% from 3 samples/day to 9 samples/day.
Le Minh Cuong
Chairman / CEO
“…Successful implementation of SMED program to reduce more than 50% of Printing machine changeover time from 90-120 minutes to 45 minutes and 30% of Lamination machine changeover time..”.
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
PT. Polymindo Permata
Plastic Extrusion
Tangerang, Indonesia
…a few examples of what we have gained during the Project:
Within 6 months of the project, the productivity of our machines has grown by 33.75% in May 2008, compared to 2007.
Simultaneously, the percentage of waste decreased by 15.8%
…SMED implementation has resulted in a 17.9% reduction in set-up time within 3 months of implementation.
Junus Sumardi
President Director
“…waste down by 15.8%, 17.9% reduction in set-up time and a 33.75% increase in machine productivity because of the implementation of your program…”
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
U-Tech
Manufacturer of high quality pre-recorded optical media (CD, DVD, Blu-Ray)
Tai Yuan Shien, Taiwan
"Not only did it achieve the promised target savings [in as short as five months], but even 10 times better … most gratif[ying] was the obvious improvement of the staff’s working attitude and their organization[al] behavior."
Steven Chang
Chairman & CEO
"promised target savings (in as short as 5 months) were even 10 times better with an obvious improvement in the staff’s working attitude …"
"The following are some comparisons before and after the project:
The DVD yield rate rose from 73.1% in July to 89.22% in December.
The CD yield rate rose from 89.5% in July to 96.22% in December.
The average output per worker rose from 68,749,000 pieces in July to 101,889,000 pieces in December.
The ROI of the project was 1,651%.
The above achievements are highly meaningful for U-Tech, since the price of oil has eroded profit capacity. [Now] U-Tech could still get soaring profits, precious and rare in such a bad time."
Rock Kuan
President, Global Manufacturing Business Unit
" …the ROI of the project was 1,651% …"
“…The average output per worker rose from 68,749,000 pieces in July to 101,889,000 pieces in December…”
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Publiambiente
Waste Collection and Disposal and Street Cleaning
Empoli, Italy
“…which within the next year, will lead to an estimated productivity improvement of approximately 30% in all our four locations.
In the TIA department (Tariffa Igiene Ambientale) a detailed and accurate observation of the activities, and the consequent improvement of the processes, led to a recovery of about 25% more users, who were not paying.”
Paolo Regini
Presidente
“…led to a recovery of about 25% more users, who were not paying…”
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Fujitsu Thailand
IT Equipment and services
Chonburi, Thailand
" … the project has successfully achieved
significant increase in productivity,
great reduction in down time (line stop).
Locator system installation to company procedure through clear role and responsibility
We found your approach very effective. With 43 calendar weeks of the program you [were] able to change our people’s behavior and improve our operation, which we have tried to achieve for the last 10 years."
Toru Ogo
President
" …with 43 calendar weeks of the program you (were) able to change our people’s behavior and improve our operation…"
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
McDonald’s Development Italy, Inc.
Restaurants
Milan, Italy
“…we have increased productivity in the restaurants overall by 21% at the same time increasing sales and achieving 1,5 million euro in annualized savings, that were clearly identified in our P&L reports.
Mario Federico
Chief of Operations
“…increased productivity in the restaurants by 21% while increasing sales…that were clearly identified in our P&L reports…”
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Schenectady International
Developer and manufacturer of chemical intermediates
Schenectady, New York, USA
"What you accomplished in months would have taken us at least five years. We had more than one million pounds of re-work, and were creating more every day. This is now being used, so we are consuming more than we are creating. Our raw material conversion numbers were incorrect, making it difficult to accurately assess the true costs of product and margin on them. This has been remedied and is being tracked … All overtime, which was out of control, is now in control and has been significantly reduced through your scheduling program. We can now identify the right number of hours to manufacture all products thus freeing up hours to put on understaffed operations. I’m also convinced these changes are systemic and as we move forward our savings will continue to grow.
Even though many of us were skeptical at first, your guarantee of "our savings must equal your fee" made this a no-brainer for us and any company for that matter …… you delivered to our bottom line more than your fee, thus I can highly recommend you to any prospective client."
Charles G. Griswold, Jr.
President and CEO
" What you accomplished in months would have taken us at least 5 years."
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Grumman Olson (now Morgan Olson)
Manufacturers of walk-in delivery vans
Sturgis, Michigan, USA
" … we have a number of individuals who have many years seniority [who] have seen "Consultants" come and go. Leaving behind what was often referred to as the "Flavor of the Month" program. Normally these programs disintegrate as fast as they were implemented, reinforcing a "See, I Told You So" attitude.
… for any new program to continue in an organization, the staff must fully understand the benefits. This … is the catalyst for the behavior changes that are necessary to be successful. [Your] training program has reinforced the need to be more "Proactive" rather than "Reactive", helping us to become "Problem Solvers" instead of "Fire Fighters." Finger pointing has been replaced with effective communication, and teamwork has taken the place of departmental division.
In summary, our substantial time investment … will pay dividends now and in the future, instrumental to our company’s continued success.
Douglas Harrison
Continuous Improvement Manager
" … we are now ‘problem solvers,’ not ‘fire fighters’ …"
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
SGA Hygiene Malaysia
Global hygiene products and paper company
Malaysia
The main objective of this program was … a cost reduction drive, and … has resulted in:
Improvement in material utilization by 18.5%
Reduction in maintenance cost by 28.6%
Labor cost reduction by 10.92%. Main contributor to this reduction overtime is the overtime cost.
The savings guaranteed in the agreement has exceeded the promise several times and we can also see the improved financial impact in our financial statements.
Peter C. Smerling
Managing Director
" … Reduction in maintenance cost by 28.6% …"
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Mono Car Styling NV
Car styling specialists
Herstal, Belgium
We have achieved significant results, and I would like to highlight a few:
Productivity improvement of over 25%
Significant reduction of lost time
Annualized savings of more than €1,000,000 (US $1,323,950)
Aldo Adorante
Administrator
"Annualized savings of more than $1.3 million."
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
ČSOB Finance
Leader in Czech financial services industry
Prague, Czech Republic
" … we have achieved the targets laid down at the beginning of the project: installation of the management systems and identified operational productivity increase of 30% (75 FTEs from … 252 employees or 38,000,000 Czech Koruna (US $2,103,500) in annual savings.
I appreciate the hard work and perseverance [of] your staff. They met stiff skepticism from our Finance staff … [but] overcame this … by demonstrating the benefits of an appropriate management system and taking a professional approach.
The installation of a new management system, and a new attitude towards effective management, could not have been achieved without your professional assistance … thanks for a job well done!"
Jan Lamser
Director and SEO
"… operational productivity increase of 30% …"
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Deringer
Custom Brokers, Warehousing & Distribution and International Freight Forwarders
St. Albans, Vermont
Despite all the changes and costs we incurred, we were able to accomplish some pretty remarkable goals.
We trained over 80 senior management, middle management and supervisory staff in the ACCESS training!
We finished 27.4% over our business plan!
Sales were up 5.1%!
Net profit was up 26%!
Wayne R. Burl
President/CEO
“…we finished 27.4% over our business plan and net profit was up 26%…”
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Velux
Window Manufacturing
Skaerbaek, Denmark
During the project we were often surprised at the positive way of implementing the IMPAC systems which were easy to adapt and install in our production philosophy.
We got many results from the project, among others,
Management system for production including
Effective stop time reporting from production processes,
Focused production (master schedule)
Waste controlling systems and rework control
Karsten Andersen
“…surprised at the positive way of implementing the IMPAC system…easy to adapt and installing our production philosophy…”
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Lone Star Steel Company
Manufacturers of steel tubing
Lone Star, Texas, USA
"As a direct result of [this] installation, uptime in the two Pipe Mills has increased from 47% to an average of 68% … an increase of 21% capacity enabling my customers to dramatically increase through-put.
In addition … we have also made improvements in maintenance spending, to date saving Lone Star Steel $1,080,000. [T]his figure reflects 160% of the promised savings for my department."
Don Belyeu
Maintenance Manager
"… uptime has increased from 47% to 68% avg. …"
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Friesland Hungaria (now Friesland Campana, Hungary)
Manufacturers and exporters of dairy products
Budapest, Hungary
"The total annual return of our investment into the project has reached 350% (instead of the originally planned €1,400,000 {US $1,853,880} it is now €250,000,000 {US $331,050.000}). The cumulative saving realized during the project totally covers the cost of initiating the project itself. The test of the improvements was clear from the beginning with no problems at all.
These significant improvements originate primarily from four areas: the savings on the number of working hours, the decrease in the loss of raw material, the improvement of the utilization of packing material and the savings on domestic energy supplies. In relation to the total need of working hours, the number of extra hours has reduced by 30%.
Finally, we have agreed on the extension of the project on two more of our factories."
Temesvári Kornél
Chairman
"Total annual ROI has reached 350%… "
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
APM Terminals
Member of the global Maersk Terminal Management Group
Port of Rotterdam, Holland
"… in the 3 years since startup, the terminal … is one of [the APM Group’s] lowest producing facilities in Europe, despite having the lowest cost per container move.
As a result of the work [February – October 2003] … our resource utilization levels [are] up with 12% and have results of 112% above plan.
In week 44 we even reached our highest average weekly production level ever … [W]e are on this moment experiencing a return on our investment of 98.5%."
Nick F. Fisher
Managing Director
"… we are operating at 112% above plan at the lowest cost per container move in the entire European organisation …"
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Extendicare Health Facilities
Long-term healthcare, outpatient rehabilitation therapy, assisted living
Milwaukee, Wisconsin, USA
"Our corporate officers told us that you would be helping us save money. To most workers these days, that means job cuts. So the first order of business was to try to reduce our employees’ anxieties. It helped that the first … team members to visit our department enlisted the help of all employees [revise] current methods … to be more efficient. The employees [felt] they were contributing to the solution. This helped our department establish a level of comfort …
As we identified problems … we implemented changes. [O]ne of our most ambitious initiatives will save Extendicare over $2 million annually.
The response has been very positive."
Lisa Feich
Purchasing Manager
"… we will save over $2 million (in purchased goods) annually …"
"… your project team initially proposed a savings potential of $5.5 million for the investment of $1,895,200 over a period over 40 weeks. I am pleased to report that cumulative savings through week 40 are now $4,864,972.00 with annualized savings of $16,692,788.00 and climbing each week."
Mel Rhinelander
Executive Vice President
"… a savings potential of $5.5 million was proposed and you are currently at $16,692,788 …"
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Skoda Praha a.s.
Car Manufacturing
Prague, Czech Republic
These days there are not only the savings that highly exceed the cost of the project realized (savings are 62.9 mil. Kc on yearly basis which is 654% of planned savings) but at the same time the implementation of the new organizational structure that was defined thanks to significant contribution of your engineers is in progress.
Ing. Stanislav Svoboda
“…savings are 62.9 Kc on yearly basis which is 654% of planned savings…”
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Dan Cake
Manufacturers and distributors of cakes and confectionery
Give, Denmark
"This is our fourth project with [you] and once again, we have been proven right in our decision to work with [you]. The monetary savings have exceeded our expectations to reach the level of 320% return on investment. We have already recovered our costs within the time frame of the project.
Company goals were set and rolled down to all management levels as to increase productivity by 25% and reduce waste by 23% while maintaining our high quality products … [and] at a very rapid pace."
Francis Bon
Chairman
"… our fourth project and our monetary savings have reached 320% ROI …"
Dan Cake
Bakers and confectioners
Give, Denmark
"[You] have delivered … sound management fundamentals starting with our vision, mission and purpose. Company goals were set and rolled down to all management levels as to increase productivity by 25% and reduce waste by 23% while maintaining our high quality products."
Francis Bon
Chairman
“… productivity up 25% … waste down 23% …”
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Shaw Industries
World’s largest carpet manufacturer (Berkshire Hathaway)
Bainbridge, Georgia, USA
"Most Fortune 500 companies focus their attention on 4 business responsibilities and commitments, and they are: (1) Right-To-Operate, (2) Financials, (3) Quality.. and (4) People Development. Your company defines a vitally important 5th business responsibility for firms that expect to survive … Business Process Improvement (BPI).
Most successful companies make incremental improvements to their financials, but very few are good at making step-change improvements because they lack the BPI redesign and re-engineering skills and competencies. The Bainbridge Plant now has those skills and competencies, thanks to your company."
Ron Henderson
Plant Manager
"You define a vital responsibility for firms that expect to survive …"
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Cobb Investment Company (now Southern Restaurant Group)
Owns and operates individual waterfront restaurants
Destin, Florida, USA
"[Your program] has led to performance improvements throughout the entire organization, including:
A reduction of labor costs by 32.76% after seasonal adjustments, generating savings in excess of $1,149,420.50 per year.
A sales improvement of 87.56%, which has resulted in our organization acquiring another $2,226,842.24 in business as we now better service our customers.
[You] delivered an excellent product that has managed indeed to change our behavior, of the management level especially.
Savings, when annualized, are 345% of costs at $2,227,000."
Thomas Kranz
Executive Vice President and CFO
"A sales improvement of 87.56% as well as a reduction in labor costs of 32.76% …"
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
FedEx
Global shipping and logistics services company
Memphis, Tennessee, USA
"I would like to share with your some of the successes my management team and our employees have already achieved during the first three weeks of working with [you].
Management meetings are much more efficient. We accomplish more in less time by staying focused.
We are learning the most effective ways to handle issues and how to confront people over non-compliance, planning for a win-win situation more often.
We are seeing behavior changes in individuals, dramatic in several cases by following [your] recommendations.
Our employees are becoming more proactive, especially through … system changes [you recommended].
We are experiencing an increase in self-awareness and evaluation, which is the beginning of behavioral change.
We have already installed overtime controls, break and lunch scheduling controls, and others, and can see the effectiveness of them in our daily productivity.
[Your] workshops attended by managers and supervisors have given us a platform to discuss and address issues which had not previously been addressed.
In summary, this joint effort between [us] has definitely been the right decision …"
Holly Price Mark Kurth Carl Bonner
Contract Manager General Manager, IRR Contract Manager
"… definitely the right decision …"
"From a skeptical start, I am pleased to report that the program has exceeded our expectations not only with regard to what has been achieved to date but the opportunity it has provided us to move forward and take on the challenges we face in our competitive market.
The financial benefits generated during the program will provide us with a 3:1 return on our investment. Undertaking this experience was certainly the right decision for us."
Roger A. Podwoski
Vice President and General Manager,
North American Logistics Operations
"The financial benefits will provide us with a 3:1 ROI …"
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
HID Corporation (now HID Global)
Global identity and security solutions
North Haven, Connecticut, USA
"Re: Your program’s effect
I am woefully late in sending you this letter detailing the efforts, professionalism and customer obsession displayed by your … team. As the President of two business units, finding employees that exhibit these traits is both a rare and wonderful thing.
I continually speak to both my staff’s about passion and "owning their work", repeatedly asking them to treat the business as if it was theirs. I have used your team as an example, a number of times, when speaking of passion.
[The team’s] efforts go beyond the incredible hours they keep. [They] have worked their way into the fabric of my organizations and in both of them have become a trusted confidant of my managing staffs. This I believe is the true gift. My people bare their professional souls to your team members, out of wanting to be better and to make every effort to not disappoint them.
It takes real talent to change human behavior; you must first know yourself and then take the time to know the person you are trying to change. The behavioral results in both locations have far exceeded my original expectations.
You should know that I was one of the three decision makers to bring [you] on board at HID. I was a bit of a skeptic. Two months into the implementation we purchased our biggest competitor, my first phone call was to [you], saying I wanted a team with me from day one to help me understand and scale the new business. [They were] there to insure a successful transition.
I am a true believer; your process has been a great lesson in the leadership of change."
Steven J. Wagner
President, HID Connecticut
"I am a true believer; your process has been a great lesson …"
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Sněžka Náchod
Maker of stitched products for cars
Náchod, Czech Republic
"… all objectives defined were at least accomplished … accumulated savings achieved to 110% of the plan in the end of the project …
… highly effective tools for planning, reporting and control of performance and idle times created in accordance with [our] specific needs … The almost incredible change is apparent on all levels of management."
Miloslav Cermak
Chairman
“… accumulated savings achieved to 110% … “
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
DEHA Ankersysteme GmbH
Makers of construction anchors
Gross-Gerau, Germany
"As a result of the management systems which were put in place we have to date been able to achieve cost savings of 1.3 million Deutsche Marks for the year.
… the production area in particular, where productivity increases of 20% and 30% have been achieved, have far exceeded our expectations."
P. Ernst
Director, Engineering
“… productivity increases of 20% and 30% … “
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
KZPP Koniecpol SA
Wood fiber products for construction
Koniecpol, Poland
"… we are observing significant changes in the actions of both managerial staff and employees. It is worth underlining that, at present, the savings in operation costs are four times above the project cost on a yearly basis, or the ‘ROI’ is 400%."
Robert Benkowski
Director
“… the ‘ROI ‘ is 400% ..”.
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Songkla Canning
Seafood canners
Bangkok, Thailand
"After 37 weeks that our people have worked with [your program], we found that not only can [it] deliver the saving it promised, but also help our people learn a new way of conducting our business."
Cheng Niruttinanon
President
“…delivers the savings it promised…”
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
BCM Electronics Corporation
Contract manufacturer
Kulim, Malaysia
"BCM is now reaping the fruits of [your] program … the installed controls made our people more aware of the cost implications of lost time, rejects, rework and scrap, thus making them more proactive in addressing such problems. Productive has improved dramatically during the course of this project, from 60% last year to an average of 90% to date."
Kim Keng Hock
Chairman
“… Productivity has improved from 60% to 90% …”
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Brigantine Services Limited
Vessel and shipyard equipment maintenance
Hong Kong, China
"… we are happy to be able to express our satisfaction with the project …
Our production and inventory management processes have changed almost completely during the course of the project, and we now have the foundation and methodology in place to perpetuate further improvements in the months and years ahead. We are also ready to capitalize on the improvements to outperform our competitors and truly create an edge when our customers."
Bjørn Højgaard
Managing Director
“… We are ready to outperform our competitors. ..”
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Versowood Group
Mechanical timber processing
Helsinki, Finland
"The financial gains brought through the project were, through measurements, an ROI over 290% as was projected at the beginning."
Pekka Kopra
Vice President
“… ROI over 290% more than was projected …”
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Leader Electronics Inc.
Electronic power supply products
Taipei, Taiwan
"… on week 31 of 34 [your team] have managed to save a total of 17,194,093 New Taiwan Dollars (US $574,496) from the production and production scheduling departments … Fantastic!
Savings and improvement highlight summary:
Total savings: NTD 17,194,093 (US $574,496)
Investment cost NTD 11,895,000 (US $397,756)
Total PAP savings: NTD 1,752,890 (US $58,615)
Average reduction in production standard time: 45%
Projected return on investment: 413%
Exponential behavior change from all internal staff involved"
C.Y. Pao
Chairman
“… Projected ROI: 413% with a 45% reduction in production standard time…”
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
OAO Veropharm
Pharmaceutical manufacturer
Moscow, Russia
"… [Your system’s] changes … allowed for achieving the goals determined at the beginning of the project:
Productivity increased in all departments by 9% to 30%
Overtime hours consumption was reduced by 8% to 10%
Throughput on the 10g ampoule line increased by 40% "
Anton Parkansky
General Director
“… Productivity increased by 9% , overtime reduced by 8% and output increased by 40% on one production line …”
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Vyksa Steel Works
Steel pipe manufacturers
Moscow, Russia
"Productivity increased by more than 30%, equipment downtime decreased significantly and also losses of working time decreased. Quality and waste control [were] reinforced. Total yearly savings amounted to 136% of the project’s planned savings; weekly savings are 101% compared to the plan …
As a result, employees now have a more pro-active and problem-solving orientation in their departments."
A.A. Sdobnikov
Director
“… Total yearly savings amounted to 136% of the project’s plan…”
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Gubahinksy Koks
Coke manufacturers
Gubaha, Russia
"There are eight weeks left till the end of the Project. I believe it is time to evaluate the Project itself …
The actual weekly cumulative savings are €1,116,569 (US $1,411,660) which is higher than the planned savings of €437,920 (US $553,653) weekly cumulative. Production increase is 8%.
… changes in our management team: the discipline is increased, and the managers learned … how to build the effective controls."
Anatoly Galkin
General Director
“… actual weekly cumulative savings are 155% of plan …”
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Zalakerámia
Ceramic tile manufacturers
Tofej, Hungary
"The savings revealed … were of a magnitude that we did not consider ourselves to be capable of realizing on our own, let alone in such a short time. [However,] during our cooperation … very important changes took place in the company which … will affect us for years to come.
Our organization structure became more simple, transparent and functional.
… productivity of labour substantially improved.
Accounts receivable are surveyed and dealt with more efficiently.
Goals setting, planning and control are no on the level where they should be …
The single best index of measurable results is that our net cost per unit [is] down to the level of 18 months ago, despite a 25% increase in energy and labour prices plus inflation."
Imre Takáts
Chairman, CEO
“… our net cost per unit is down to a level of 18 months ago despite a 25% increase in energy and labour prices plus inflation…”
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Picvue Electronics
Semi-Conductors and Electronic Components
Hsin Chu, Taiwan
"The financial benefits generated during the program were impressive, as we have saved more than originally projected … we got back almost 200% of our investment at the end of the project. The behaviour changes in our people, clarity of the company’s objectives, objective performance measurements, and more proactive management are the major output of these changes."
Dr. Jacob W. Lin
President & CEO
“… we got back almost 200% of our investment by the end of the project ..”
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Elektrobudowa SA
Power and petrochemical construction and installation services
Mikolow, Poland
"Since the beginning of our project I have been amazed and awed by the style of work of your personnel, who are focused on accomplishing the goals stated in the contract. The newly prepared and implemented management system helped to increase the productivity of different areas by 20-30% and thus reduced our production costs."
Henryk Wojtyczka
Plant Director
“… amazed and awed by your work …”
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
Pal-Inalfa
Automobile body panels
Vráble, Slovakia
"Besides the significant cost reductions of more than 20 million Slovakian Koruna (US $500,000 approx.) on an annual basis, we also managed to introduce new management systems and to change the attitude and problem solving capacity of management and organization.
With 200 employees less, especially in the overheads, we still do the same turnover but with a much better quality and delivery performance. Now the company is ready for growth, which is imminent."
Fred L.M. Welschen
President
“… 200 people less, we still do the same turnover but with better quality and delivery performance …”
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *
TONI HOLDINGS AG
Ice cream and dairy products
Zurich, Switzerland
"The challenging goals … which we set when the project started were achieved in nearly all departments … In some of the installation areas the ambitious goals were surpassed by to 30%. [A]mong other things, the following:
Basel goods inwards; Goal: 9.4 containers per hour, actual: 10.18 containers per hour.
Warehouse Lausanne; Goal: 64 positions per hour, actual: 64.59 positions per hour.
Basel telephone sales; Goal: 944 Sw.Francs (US $651) per delivery; actual: Sw.Francs 987.50 (US $ 681) per delivery.
Peter Aegerter
CEO
“… ambitious goals were surpassed up to 30% …”
* * * * * * * * * * * * * * * * * * * * * * * * * * * * * * *